MELBA / GREEN STREET DRAINAGE IMPROVEMENT

  • Location: Jacksonville, FL

  • Client: City of Jacksonville and Jacksonville Electric Authority (JEA)

  • Engineer: Stone Joca & Associates

  • Contract Value: $3,516,431

  • Project Details:

  • Installation of 4,167 LF of new storm drain, which included 60” RCP under an existing roadway.

  • Installation of 5,200 LF of new watermains, excavation of a new retention pond.

  • Installation of an arch culvert underneath a roadway and adjacent to an existing residence.

  • Surface improvements included road reconstruction, milling and resurfacing and new sidewalk construction.